Planning Schedule Response Edits | Recommended Process | Steps |
---|---|---|
A few Points In Time (PITs) | Manually via the SCMP UI MCV page- Time Buckets | 1. On the MCV page, enter the Planning Schedule Response Qty values for each specific date. 2. Click the Update button. |
A few Points In Time (PITs) Plus include a Response Note | Manually via the SCMP UI MCV page- Data Measure | 1. On the MCV page, click the Planning Schedule Response Qty data measure name to pop open the PIT Info window. 2. Enter the Quantity values for each specific date. 3. Enter the Response Note and/or Reason Code for each specific date. 4. Click the Update button. |
A few to All Points In Time (PITs) where new PIT data will match existing data | Manually via the SCMP UI MCV page- Copy PIT Function | 1. On the MCV page, select the desired Collabs and click the Copy PITs tab. 2. Set desired Start Date and End Date. 3. Select the appropriate Source and Target Data Measure from the pull down menu. 4. Click the Copy button. 5. Click the OK button. |
Numerous Points In Time (PITs) – Because the Planning Schedule is new or needs to be extensively changed | Download/Edit/Upload Excel spreadsheet | 1. Click Download Plan Schedules and follow the normal download process for all the items that you don’t already have a Planning Schedule Response and/or items whose Planning Schedule Response needs to be extensively changed. 2. Edit the downloaded file to reflect your new or changed Planning Schedule Response, including a Reason Code if applicable. 3. Click Upload Files and follow the normal upload process. |
Response Input
This information is for Providing Partners ONLY. To input data via time buckets:
1 Enter data into the appropriate time buckets. Click the Update button.
2. Click the OK button to acknowledge the changes.
To input data via the Data Measures:
1. Click the Planning Schedule Response Qty data measure name.
2. In the Quantity column enter the vales for the appropriate date buckets.
3. Optional, add a Response Notes and/or Reason Code.
4. Click the Submit button. Click the OK button to acknowledge the changes.