Boeing 787 SCMP Publish Planning Schedules

The Consuming Partner publishes a Planning Schedule to indicate their requirements to the Providing Partner and Boeing. The Planning Schedule data includes part number, quantity, date needed, and delivery site.
The Consuming Partner enters the Planning Schedule:
– Manually via the SCMP User Interface (UI) in the Multi- Collab View (MCV) page.
If manually created, the Consuming Partner should change the Schedule Status to New to let the Providing Partner know it is ready for a response:
– Uploading an Excel spreadsheet.
– Through B2B transaction
The Planning Schedule has an 18-month planning horizon:
– The user interface defaults to about 28 weeks of daily ‘time buckets’ or columns.
– The timeline view can be changed to show the data as weekly or monthly time buckets.  The underlying data remains the same.

Guidelines

Planning Schedule EditsRecommended ProcessSteps
A few Points In Time (PITs)Manually via the SCMP UI MCV page- Time Buckets1. On the MCV page, enter the Planning Schedule Qty values for each specific date.

2. Click the Update button.
A few Points In Time (PITs)

Plus include a Receiver Reference Number and Mfg. Line Number
Manually via the SCMP UI MCV page- Data Measure1. On the MCV page, click the Planning Schedule Qty data measure name to pop open the PIT Info window.

2. Enter the Quantity values for each specific date.

3. Enter the Receiver Reference Number and Mfg. Line Number for each specific date.

4. Click the Update button.
A few to All Points In Time (PITs) where new PIT data will match existing dataManually via the SCMP UI MCV page- Copy PIT Function1. On the MCV page, select the desired Collabs and click the Copy PITs tab.

2. Set desired Start Date and End Date.

3. Select the appropriate Source and Target Data Measure from the pull down menu.

4. Click the Copy button.

5. Click the OK button.
Numerous Points In Time (PITs)
– Planning Schedule is new or needs to be extensively changed
Download/Edit/ Upload Excel spreadsheet1. Click Download Plan Schedules and follow the normal download process for all the items you don’t already have a Planning Schedule and/or items whose Planning Schedule needs to be extensively changed.

2. Edit the downloaded file to reflect your new or changed Planning Schedule, including setting the Receiver Reference Number and Mfg. Line Number if appropriate.

3. Click Upload Files and follow the normal upload process.