To activate or deactivate a planning schedule:
1. On the left Navigation Tree, go to Supply Planning, Activate/Deactivate Items.
2. Enter your search criteria. Click Search.
3. To Activate a Collab, delete the date in the Inactive Date column.
4. To Deactivate a Collab, enter the date in the Inactive Date column.
NOTES:
-
- The date must be in the future, not today or a past date.
- The Collab will become inactive on the specified date during the nightly run.
- The system automatically checks the box to select the line.
5. Click the Save button.
Alternatively, follow the steps below to activate/deactivate:
1. On the MCV page, click the View Collaboration Details button.
2. Click the Collab Attribute option.
3. To Activate a Collab, delete the date in the Inactive Date box.
4. To Deactivate a Collab, enter the date in the Inactive Date box.
NOTES:
-
- The date must be in the future, not today or a past date.
- The Collab will become inactive on the date during the nightly run.
5. Click the Update button.